Binder · priced so we are never blind
$5,000,000 master budget and collateral register
Every equipment price in this file is an estimate for planning. It is not a vendor quote, not an appraisal, and not a bid. Terry + industrial + structural + manufacturing engineering write specifications and RFQs before a major machine is purchased. Replace this schedule with quoted amounts before SBA authorization.

Master buckets — $5,000,000
| Category | Program | Amount | Honesty |
|---|---|---|---|
| 7-acre plant | 504-eligible | $500,000 | Raw land. 7-acre plant occupancy on the researched 12.70-acre tract at 55197 Old Gentilly Road — across from NASA Michoud at 13800, same street as Folgers at 14601. Listing ask $275,000 (not a purchase). $500,000 covers closing, survey, geotech, and a higher contract. Slack is not extra dirt and not a street grid. |
| 40,000-SF high-bay factory building | 504-eligible | $1,000,000 | $25/SF planning figure for a used or relocated ~170' × 235' high-bay — crane-capable industrial shell, not new Class A construction. Ugly and functional. Width is the 207' strip; depth is the assembly lanes. The extra 10,000 SF is production room, not a prettier warehouse. |
| Site development / utilities / yard | 504-eligible | $200,000 | Yard finish on a raw 7-acre pad across a developed industrial street — gravel, short taps, stormwater, fence, yard lights. NASA / Folgers / Entergy already sit on utilities. Streets already exist. Not fill. Not a tap letter. Not clearing 12.7 acres as a campus. Civil unknowns stay a closing condition. |
| Core manufacturing equipment | 7a-capex | $700,000 | The machines that turn purchased inputs into a house: ICF, CNC/hot-wire, steel/rebar, cassettes, MEP, fixtures, finishing, air, QC lab, safety kit. ICF moulding and CFS roll-forming stay RFQ cells. No fiber laser. No humanoids. Helical piers stay bought. |
| AI + automation systems / cells | 7a-capex | $550,000 | Labor-attacking automation: material movement, computer vision QC, kitting, guided stations, assisted ICF, assisted steel/rebar, sensors/PdM, PLC integration. Not a $500k AI-factory brand. Not 100 robots. AI thinks → MES coordinates → PLC executes → cameras verify → humans handle exceptions. |
| Material handling / cranes | 7a-capex | $150,000 | Gantry/jib, two used sit-down forklifts, pallet jacks, four dock levelers, racks. Reach truck is a Year-1 rental if rack height needs it — not owned on Day 1. Docks are how three-shift ships — not a later add. |
| Trucks / trailers / field erection fleet | 7a-capex | $100,000 | One used Class 8, two flatbeds, securement, rigging. Pickup, telehandler, second tractor, step-deck, mini-ex, skid and compactors are Year-1 rentals until the line earns them. Mobile crane remains contracted. |
| Engineering / product development | 7a-wc | $225,000 | Do not starve this. PE stamps, typicals, Ameridura ICF geometry, CFS joist family, BOM, first-article engineering of four launch models. The 2,500 and 2,750 stay engineered on-deck. Not a year of a 12-person engineering department. |
| Certification / testing / code approvals | 7a-wc | $150,000 | Do not starve this. Louisiana first. Ameridura ICF ASTM / ICC-ES start. 50-state matrix is a stub. Not 50 certificates on Day 1. AI does not stamp. |
| Digital manufacturing / MES / BIM / AI / QMS | 7a-wc | $200,000 | The factory nervous system: Autodesk BIM, MES/ERP, production database, machine connectivity, scheduling, inventory, barcode/RFID, QC software, dashboards, digital-twin foundation, AI agents on commercial models. Not 15 AI subscriptions. Not a custom $600k platform. The consumer site sits in the marketing launch line. |
| Initial inventory / materials | 7a-wc | $175,000 | Safety stock of ICF forms, galvanized coil, rebar, openings, MEP. The first-article house is production COGS. Demonstration pad/set sits in the $100k models line. |
| Core executive / engineering payroll during startup | 7a-wc | $350,000 | Elite core, not a headquarters. Founder draw + manufacturing/ops chief + Chief AI & Digital Manufacturing + controller + quality (fractional) + industrial automation engineer + supply chain, with burden. Plant manager and EHS hire at commissioning. Not six $250k executives. |
| Insurance / legal / accounting / permits | 7a-wc | $100,000 | GL, product, WC, auto, property, inland marine, umbrella, cyber, entity work, CPA, permits. |
| Ameridura Homes marketing launch | 7a-wc | $100,000 | Website, brand, kits, CRM and first digital launch. Ongoing marketing lives on the operating P&L (Y1 floor still $200k). |
| Model homes / demonstration units | 7a-wc | $100,000 | Not three houses at factory COGS. Factory tour is the showroom. This line is the first-article pad/set/furnishings at the gate, visitor path, and a sales desk inside the hall. The house itself is production COGS. |
| Operating / working-capital reserve | 7a-wc | $400,000 | Cash is an automation system. Payroll float, utilities, receivables lag, contracted crane, Year-1 rentals, oversize permits, warranty, first-article scrap. A late machine or a slow certification is why this exists. |
| Total uses (ceiling) | $5,000,000 |
- 504-eligible (land + building + site): $1,700,000
- 7(a) capex (core manufacturing + automation + handling + fleet): $1,500,000
- 7(a) working capital (under the $2M ITL cap): $1,800,000
- $1,800,000 of 7(a) working capital for the first 12–18 months of plant stand-up. The ask is sized to engineering, certification, digital backbone, payroll float, initial inventory, insurance, marketing launch, the first-article pad, and $400,000 of unspent cash reserve. Draws follow invoices. A 12-month burn schedule is in this plan.
- SBA 504 on land, building and site ($1.70 million) and SBA 7(a) on equipment, automation, fleet, startup and working capital ($2.80 million). Sponsor equity $500,000. Total project $5.0 million. 7(a) working capital is $1.80 million of startup operating capital. Working Capital Pilot is a later facility after 12 months of operations — not this application.
- Crane access is a contracted operating cost until utilization supports ownership.
Site and building — what $1.70 million actually builds
Located in the Michoud industrial corridor adjacent to NASA Michoud Assembly Facility at 13800 Old Gentilly. The 7-acre plant pad across that street is raw land. Folgers, Entergy, and the Michoud Boulevard warehouses already sit on utilities; Kern paid $2.4 million for those warehouses in 2022–2023. $200,000 of site work is a planning estimate for yard finish and a short tap — not a contractor bid, not fill, not a new road.
We always use NASA’s address as the pin — 13800 Old Gentilly Road. The plant is directly across that street. The strip is already built: Folgers, Entergy, Michoud Boulevard warehouses. Kern Studios paid $2.4 million in 2022–2023 for those warehouses. 55197 is the vacant tract across from 13800 — not owned. The pad is still raw. $200,000 is still yard finish and a short tap, not fill. Get the survey, the flood map, and the utility letters before we close.
12 acres was an old working number for the factory. It is not this file. The locked plant is 7 acres. 12.70 acres is the researched listing across from NASA — the tract, not the factory size. If 55197 is the contract, Phase I occupies 7 acres of that 12.70-acre industrial parcel. The remaining ~5.7 acres stay as same-parcel truck yard / house staging / a future pad. Not lots. Not a street grid. Not a 12-acre factory in the brochure. Do not buy extra dirt on this note in order to subdivide it. Old Gentilly Road and Michoud Boulevard already bound the listing. Both are paved. This file does not build those roads. We still have to reach Old Gentilly — driveway, culvert, and whatever the City requires at the apron — and we still have to get power, water, and sewer onto the pad. Across the street is not the same as stubbed at the transformer. Researched addresses.
7-acre plant
$500,000
Used ~40,000-SF shell
$1,000,000
$1,000,000 for ~40,000 SF is $25/SF — a planning estimate for a used or relocated ~170' × 235' high-bay on a crane-capable industrial slab, docks, and plant power. It is not an all-in finished factory and not new Class A industrial construction. Width is the 207' Old Gentilly strip. The extra 10,000 SF is production room. The slab assumes a prepared pad. Raw-land fill is not inside the slab line. Line items replace the round number.
Factory yard
$200,000
Site line — $200,000
This $200,000 is a planning estimate for yard finish on a pad assumed to be buildable: gravel truck drives, stormwater for that yard, short utility taps, fence, yard lights. It is not a contractor bid. The corridor thesis is that NASA / Folgers / Entergy already made the street industrial, so a short tap is the right class of spend if the letters say the mains are at this ditch. Geotech, FEMA zone, wetlands, survey, and utility letters replace this paragraph before closing. If those numbers come in above $200,000, the project budget is revised.
| In this yard line | Amount |
|---|---|
| Pad / yard clearing and rough grade (not 7-acre mass fill) | $40,000 |
| Drainage and stormwater for the yard | $32,000 |
| Heavy truck drives and aggregate yards | $48,000 |
| Short utility taps (water, sewer/septic, electric, gas) — not a long main | $45,000 |
| Fencing, gates, exterior lighting | $18,000 |
| Minimal employee parking | $5,000 |
| Signage | $2,000 |
| Trailer and finished-product gravel staging | $10,000 |
| Site total | $200,000 |
This yard includes
- Limited pad / yard clearing and rough grade — not mass fill of 7 acres.
- Stormwater / drainage for a gravel industrial yard.
- Heavy truck drives and aggregate yards. Gravel first. Asphalt later.
- Short utility connections if the mains are at or near the property line — which the MLS claims, and which the letters must confirm. Not a mile of main, not a lift station, not a new substation.
- Fence, gates, and yard / security lighting. Not municipal streetlights down a new road. Old Gentilly is already lit as an industrial spur.
- A few employee parking spaces, a sign, and gravel staging for trailers and finished houses.
This yard does not include
- Making raw land buildable — fill, surcharge, elevation to flood / levee grade.
- Clearing 12.7 acres as a campus, or mass-clearing all 7 acres beyond the pad and yard.
- Public or private streets with curb, gutter, sidewalk, and street lighting. Those streets already exist.
- A paved industrial park or pretty campus.
- Long utility extensions, a lift station, or a new electrical service drop from far off-site — the point of this corridor is that should not be the job. Letters still required.
- Wetlands mitigation, a full detention lake, or off-site road improvements the City assesses.
- Developing the remainder acres into lots, a model-home street, or a second plant pad.
Building line — $1,000,000
| In this $1,000,000 | Amount |
|---|---|
| Used / relocated steel high-bay shell (~40,000 SF, 170' × 235') | $520,000 |
| Reinforced industrial slab (crane / fixture loads) | $205,000 |
| Overhead doors and four truck docks | $68,000 |
| Offices, lockers, break room, first aid, training | $45,000 |
| Electrical service, panels, LED, generator / ATS, utility drops | $85,000 |
| Fire alarm and sprinkler | $45,000 |
| HVAC for occupied areas + plant ventilation share | $20,000 |
| Security cameras and access control | $12,000 |
| Building total | $1,000,000 |
If you meant streets and 12 acres
$500,000 land + $1,000,000 building + $200,000 yard
What this $5,000,000 file actually funds
7 acres occupied on the researched Old Gentilly tract, a used/relocated 40,000-SF shell, and $200,000 of yard finish. Streets are already there. That $200,000 works if fill is modest and the tap letters match the MLS.
Often $0.8–$2.5 million of civil — on top of land — before the shell, if fill and wetlands go badly. Does not fit in this $200,000.
What still can blow the civil number on this raw pad
Fill / elevation, wetlands, and a tap that is not actually at the ditch. The corridor being developed does not grade 55197 for free.
Easily $1.5–$4 million+ of infrastructure, before any building. Not this application.
Clearing 12.7 acres and putting in streets and streetlights
A small industrial park or a subdivision. Old Gentilly and Michoud Boulevard already bound this lot. Doing that work anyway is separate capital. Not this factory note.
Demonstration — $100,000. The factory is the showroom.
The factory is the fourth demonstration. Customers see The 1,250 first article at the gate and the line that made it. Do not spend capital landscaping three expensive model houses.
The $100,000 demonstration line does not buy three houses. The first-article house is production COGS. This line is pad, set, furnishings, a visitor path, and a sales desk inside the factory. Customers walk raw material → ICF → assembly → finished home.
The 2,100, The 2,500 and The 2,750 remain engineered on-deck. They are not three extra walkthroughs on this note.
| Demonstration line | Amount |
|---|---|
| First-article demonstration pad, utilities and set at the factory gate | $45,000 |
| Furnishings, signage and visitor path for the first-article house | $18,000 |
| Factory tour path, visitor PPE, viewing platform | $15,000 |
| Sales office fit-out inside the high-bay (not a separate showroom) | $12,000 |
| Photography / film of production + first article | $10,000 |
| Inside the $5,000,000 | $100,000 |
Working capital — $1,800,000 of 7(a) WC (under the $2,000,000 cap)
The plan does not say “Ameridura needs enough cash to manufacture every house it sells.” The plan says Ameridura uses customer deposits, operating capital and a revolving working-capital facility to finance the production cycle between contract award and final delivery and payment.
The ask is sized to engineering, certification, digital backbone, payroll float, initial inventory, insurance, marketing launch, the first-article pad, and $400,000 of unspent cash reserve. Draws follow invoices. A 12-month burn schedule is in this plan.
Phase I uses stay $5,000,000. The 7(a) working-capital stack is $875,000 spent to stand the plant up and $925,000 of operating float. Those two numbers are $1,800,000. Cash reserve is $400,000 because a factory that stops is more expensive than a prettier machine. The $100,000 Ameridura Homes launch is a desk, not CAC.
A. Startup operating working capital is this note. B. Production / order working capital is 7(a) Working Capital Pilot after twelve months. WCP is not part of the $5,000,000 Phase I ask. The company has zero months of operations.
This application — SBA 7(a) working capital inside the $5.0 million Phase I project. WCP is not part of the $5,000,000 Phase I ask. The company has zero months of operations. SBA currently limits WCP to businesses with at least 12 full months of operations before filing, able to produce timely financial statements plus accounts-receivable aging, accounts-payable aging, and inventory reports.
Spent launch
$875,000
Engineering, certification, digital backbone, insurance, marketing, demonstration pad
Inventory
$175,000
Steel, foam, openings, MEP — raw materials. The first-article house is production COGS.
Payroll float
$350,000
Elite core during startup. Floor hires at commissioning.
Operating reserve
$400,000
Unspent cash. Shock absorber. Cash is an automation system.
| ITL working-capital stack | Kind | Amount |
|---|---|---|
| Engineering / product development | Spent launch | $225,000 |
| Certification / testing / code approvals | Spent launch | $150,000 |
| Digital manufacturing / MES / BIM / AI / QMS | Spent launch | $200,000 |
| Initial inventory / materials | Operating float | $175,000 |
| Core executive / engineering payroll during startup | Operating float | $350,000 |
| Insurance / legal / accounting / permits | Spent launch | $100,000 |
| Ameridura Homes marketing launch | Spent launch | $100,000 |
| Model homes / demonstration units | Spent launch | $100,000 |
| Operating / working-capital reserve | Operating float | $400,000 |
| ITL working capital | $1,800,000 |
| Cash cycle | Dollars | Honesty |
|---|---|---|
| Mix-weighted factory-gate invoice (FY2027) | $179,947 | Living SF × $112. Designed mix — not a $150k planning ASP. |
| 25% deposit before production release | $44,987 | Customer cash. Taken before the house is released to the line. |
| Mix-weighted designed factory cost (30 homes) | $125,320 | PRE-PRODUCTION TARGET — NOT HISTORICAL COST. Designed BOM × this year’s SKU mix. |
| Production gap per house (cost − deposit) | $80,333 | This is the manufacturing working-capital cycle — not 75% of cost, and not the full invoice. |
| 60-day WIP at 4–6 homes/month, no deposits | $1,253,200 | 10 houses in the bay and on the dock at designed cost. |
| Same 60-day WIP after 25% deposits | $803,330 | 10 × the production gap. The operating target on this floor. |
| 90-day WIP, no deposits (today’s pipeline) | $1,879,800 | Zero committed homes. This is why the file keeps $400,000 of unspent cash inside the $1.8 million. |
Iron rented in Year 1 so cash can float houses — $195,000
| Not purchased in Phase I | Would have cost | Why it is a rental |
|---|---|---|
| Second Class 8 tractor (older used) | $42,000 | One owned tractor plus contracted overflow until the second truck earns its keep. |
| Step-deck trailer | $26,000 | Rent when a load is height-sensitive. Two flatbeds cover the standard module. |
| Reach truck | $22,000 | 40,000 SF with sit-down forklifts and pallet jacks. Rent if rack height needs it. |
| Mini excavator (used) | $14,000 | Foundation and utilities are a rental until utilization pays. |
| Skid steer (used) | $11,000 | Grade and materials — rented with the mini-ex. |
| Utility / equipment trailer | $7,000 | Crew support is a rental until the field book is real. |
| Plate compactors | $3,000 | Foundation prep tools. Buy when the set crew is full-time. |
| Telehandler (used) | $32,000 | Set and yard. Owned iron waits until utilization pays — not a Day-1 purchase. |
| Heavy-duty pickup | $38,000 | Field ops rental until the set book is real. |
Equipment cells — $1,700,000
| Cell | Bucket | Lines | Amount |
|---|---|---|---|
| ICF assembly | mfg | 6 | $84,000 |
| Rebar | mfg | 7 | $105,000 |
| Steel fab | mfg | 11 | $108,000 |
| Floor + roof | mfg | 8 | $96,000 |
| MEP prefab | mfg | 12 | $68,000 |
| Kitchen + bath | mfg | 7 | $42,000 |
| Windows + doors | mfg | 4 | $16,000 |
| Finishing | mfg | 6 | $38,000 |
| Concrete (field) | mfg | 7 | $32,000 |
| QC laboratory | mfg | 9 | $40,000 |
| Maintenance | mfg | 7 | $25,000 |
| Utilities (air) | mfg | 4 | $30,000 |
| Safety | mfg | 5 | $16,000 |
| Material movement | automation | 3 | $115,000 |
| Computer vision QC | automation | 3 | $90,000 |
| Automated kitting | automation | 3 | $70,000 |
| Guided stations | automation | 2 | $45,000 |
| Assisted ICF cell | automation | 3 | $90,000 |
| Assisted steel / rebar | automation | 3 | $70,000 |
| Predictive maintenance | automation | 2 | $35,000 |
| Controls / integration | automation | 2 | $35,000 |
| Material handling | handling | 7 | $150,000 |
| Transport | fleet | 3 | $91,000 |
| Site erection | fleet | 1 | $9,000 |
| Digital factory | tech | 13 | $73,500 |
| Software year-1 | tech | 10 | $126,500 |
Every machine, tool, and vehicle — SKU priced
148 lines. Qty × unit = extension. Vendor class is a search start, not a bid.
| SKU | Item | Qty | Unit | Ext. | Serial / VIN | Power / SF |
|---|---|---|---|---|---|---|
| EQ-ICF-CNC | CNC foam / hot-wire cutter ICF assembly · U.S. foam CNC (Hotwire / similar) or equivalent | 1 | $38,000 | $38,000 | TBD at invoice | 240V 1Ø/3Ø · 200 |
| EQ-ICF-HW | Secondary hot-wire station ICF assembly · Domestic foam-cut supplier | 1 | $6,000 | $6,000 | TBD at invoice | 120/240V · 80 |
| EQ-ICF-TABLES | ICF assembly tables ICF assembly · U.S. fab / in-house steel | 4 | $2,500 | $10,000 | TBD at invoice | none · 400 |
| EQ-ICF-JIGS | Wall jigs and alignment fixtures ICF assembly · In-house + local fab | 1 | $20,000 | $20,000 | TBD at invoice | none · 600 |
| EQ-ICF-FIXTURES | Corner / T / end / buck / lintel fixtures ICF assembly · In-house + local fab | 1 | $7,000 | $7,000 | TBD at invoice | none · 200 |
| EQ-ICF-LABEL | ICF labeling / barcode station ICF assembly · Zebra / Honeywell class | 1 | $3,000 | $3,000 | TBD at invoice | 120V · 40 |
| EQ-RB-CNC | CNC rebar bender Rebar · U.S./NA dealer (KRB, Schnell, or used domestic) | 1 | $58,000 | $58,000 | TBD at invoice | 480V 3Ø · 250 |
| EQ-RB-CUT | Rebar cutter Rebar · U.S. construction-equip dealer | 1 | $14,000 | $14,000 | TBD at invoice | 480V 3Ø · 80 |
| EQ-RB-STIR | Stirrup bender Rebar · NA dealer | 1 | $12,000 | $12,000 | TBD at invoice | 240/480V · 100 |
| EQ-RB-STR | Straightener / decoiler (right-sized / used) Rebar · Used industrial | 1 | $8,000 | $8,000 | TBD at invoice | 240V · 120 |
| EQ-RB-JIG | Cage / wall / opening / beam jigs Rebar · In-house fab | 1 | $8,000 | $8,000 | TBD at invoice | none · 400 |
| EQ-RB-TIE | Automatic rebar tying tools Rebar · MAX / similar | 2 | $2,000 | $4,000 | TBD at invoice | battery · portable |
| EQ-RB-TAG | Rebar tagging / mill-cert station Rebar · Label + rack | 1 | $1,000 | $1,000 | TBD at invoice | 120V · 60 |
| EQ-ST-PLASMA | CNC plasma table (4×8 class) Steel fab · U.S. (Hypertherm table class / used) | 1 | $38,000 | $38,000 | TBD at invoice | 480V 3Ø + air · 300 |
| EQ-ST-IRON | Ironworker Steel fab · Scotchman / similar U.S. | 1 | $12,000 | $12,000 | TBD at invoice | 230/460V · 80 |
| EQ-ST-SHEAR | Hydraulic shear (small) Steel fab · Used industrial | 1 | $8,000 | $8,000 | TBD at invoice | 230V · 80 |
| EQ-ST-BRAKE | Press brake (40–60T used) Steel fab · Used U.S. dealer | 1 | $12,000 | $12,000 | TBD at invoice | 230/460V · 150 |
| EQ-ST-BAND | Band saw Steel fab · U.S. industrial | 1 | $5,000 | $5,000 | TBD at invoice | 230V · 40 |
| EQ-ST-COLD | Cold saw Steel fab · U.S. industrial | 1 | $3,000 | $3,000 | TBD at invoice | 230V · 30 |
| EQ-ST-DRILL | Drill press + magnetic drills Steel fab · Milwaukee / similar | 1 | $3,500 | $3,500 | TBD at invoice | 120/230V · 40 |
| EQ-ST-MIG | MIG welders Steel fab · Miller / Lincoln U.S. | 4 | $2,500 | $10,000 | TBD at invoice | 230/460V · weld bay |
| EQ-ST-TIG | TIG welder Steel fab · Miller / Lincoln U.S. | 1 | $2,500 | $2,500 | TBD at invoice | 230V · weld bay |
| EQ-ST-TABLES | Welding tables, fixtures, curtains Steel fab · U.S. weld-table | 1 | $6,000 | $6,000 | TBD at invoice | none · 400 |
| EQ-ST-FUME | Welding fume extraction (cell) Steel fab · Lincoln / Donaldson class | 1 | $8,000 | $8,000 | TBD at invoice | 230V · ducted |
| EQ-FR-PANEL | CNC panel saw Floor + roof · U.S. wood CNC / used panel saw | 1 | $18,000 | $18,000 | TBD at invoice | 230/460V · 250 |
| EQ-FR-BEAM | Beam saw Floor + roof · Construction saw dealer | 1 | $7,000 | $7,000 | TBD at invoice | 230V · 80 |
| EQ-FR-SAWS | Table / miter / chop saw package Floor + roof · SawStop + DeWalt class | 1 | $6,000 | $6,000 | TBD at invoice | 120/230V · 120 |
| EQ-FR-ROUTER | CNC router (shared with cabinets) Floor + roof · U.S. CNC (ShopSabre / similar class) | 1 | $18,000 | $18,000 | TBD at invoice | 230V · 200 |
| EQ-FR-TABLES | Floor and roof assembly / framing tables Floor + roof · In-house + truss-table analog | 1 | $22,000 | $22,000 | TBD at invoice | air · 800 |
| EQ-FR-AIR | Pneumatic nailers / screw systems Floor + roof · Paslode / Milwaukee class | 1 | $6,000 | $6,000 | TBD at invoice | air / battery · portable |
| EQ-FR-ADH | Adhesive and membrane stations Floor + roof · Construction supply | 1 | $4,000 | $4,000 | TBD at invoice | 120V · 120 |
| EQ-FR-LIFT | Floor / roof lifting fixtures Floor + roof · In-house + rigging shop | 1 | $15,000 | $15,000 | TBD at invoice | none · staging |
| EQ-EL-CUT | Automatic wire cutter / stripper MEP prefab · Komax class / Schleuniger used | 1 | $8,000 | $8,000 | TBD at invoice | 120V · 40 |
| EQ-EL-CRIMP | Crimp / terminal / wire-label kit MEP prefab · Panduit / Brady class | 1 | $4,000 | $4,000 | TBD at invoice | 120V · 40 |
| EQ-EL-BOARD | Harness boards and electrical benches MEP prefab · In-house | 1 | $5,000 | $5,000 | TBD at invoice | 120V · 200 |
| EQ-EL-COND | Conduit bender + cutter MEP prefab · Greenlee class | 1 | $3,500 | $3,500 | TBD at invoice | 120V / hyd · 40 |
| EQ-EL-TEST | Electrical test kit (megger, GFCI, continuity) MEP prefab · Fluke class | 1 | $4,500 | $4,500 | TBD at invoice | battery · QC |
| EQ-EL-PANEL | Panelboard assembly station MEP prefab · In-house + Square D / Eaton components | 1 | $5,000 | $5,000 | TBD at invoice | 120V · 80 |
| EQ-PL-PEX | PEX cutter / expander / crimp kit MEP prefab · Uponor / Milwaukee class | 1 | $3,500 | $3,500 | TBD at invoice | battery · portable |
| EQ-PL-MAN | Plumbing manifold / module fixtures MEP prefab · In-house | 1 | $5,000 | $5,000 | TBD at invoice | none · 150 |
| EQ-PL-TEST | Plumbing pressure / leak test station MEP prefab · Test-pump dealers | 1 | $3,000 | $3,000 | TBD at invoice | 120V · 40 |
| EQ-HV-PLASMA | Small duct plasma cutter MEP prefab · U.S. HVAC plasma (used/new) | 1 | $12,000 | $12,000 | TBD at invoice | 230V + air · 150 |
| EQ-HV-PITT | Pittsburgh lock + brake MEP prefab · Lockformer class / used | 1 | $10,000 | $10,000 | TBD at invoice | 230V · 120 |
| EQ-HV-SEAM | Seamer / insulation / seal station MEP prefab · HVAC supply | 1 | $4,500 | $4,500 | TBD at invoice | 120V · 80 |
| EQ-CB-SAW | Cabinet panel saw Kitchen + bath · Used SCM / Altendorf class | 1 | $10,000 | $10,000 | TBD at invoice | 230V · 150 |
| EQ-CB-EDGE | Edgebander Kitchen + bath · Used Holz-Her / SCM class | 1 | $12,000 | $12,000 | TBD at invoice | 230V · 120 |
| EQ-CB-BORE | Hinge boring / drilling Kitchen + bath · Blum / Maggi class | 1 | $6,000 | $6,000 | TBD at invoice | 230V · 80 |
| EQ-CB-ASM | Cabinet assembly tables and clamps Kitchen + bath · In-house | 1 | $5,000 | $5,000 | TBD at invoice | air · 200 |
| EQ-CB-HW | Hardware insertion station Kitchen + bath · Cabinet supply | 1 | $2,000 | $2,000 | TBD at invoice | 120V · 40 |
| EQ-CB-TOP | Countertop cutting (bridge saw used) Kitchen + bath · Used stone saw — not waterjet | 1 | $4,000 | $4,000 | TBD at invoice | 230V + water · 150 |
| EQ-CB-BATH | Shower / waterproofing station Kitchen + bath · Schluter / similar system tools | 1 | $3,000 | $3,000 | TBD at invoice | 120V · 120 |
| EQ-WD-TABLE | Glazing / window assembly tables Windows + doors · In-house | 1 | $4,000 | $4,000 | TBD at invoice | none · 150 |
| EQ-WD-LIFT | Glass suction lifters Windows + doors · Wood’s / similar | 1 | $3,500 | $3,500 | TBD at invoice | battery · portable |
| EQ-WD-SEAL | Sealant dispensing Windows + doors · U.S. dispensing | 1 | $3,000 | $3,000 | TBD at invoice | 120V / air · 40 |
| EQ-WD-DOOR | Door fixtures and hardware station Windows + doors · In-house + hardware | 1 | $5,500 | $5,500 | TBD at invoice | 120V · 120 |
| EQ-FN-BOOTH | Paint spray booth Finishing · U.S. booth (Garmat class / used) | 1 | $16,000 | $16,000 | TBD at invoice | 230V + exhaust · 400 |
| EQ-FN-SPRAY | Airless / HVLP sprayers Finishing · Graco class | 1 | $5,000 | $5,000 | TBD at invoice | 120/230V · booth |
| EQ-FN-DW | Drywall cutting, lifts, taping tools Finishing · Construction supply | 1 | $6,000 | $6,000 | TBD at invoice | 120V · 200 |
| EQ-FN-FL | Flooring / tile saws Finishing · MK / similar | 1 | $4,000 | $4,000 | TBD at invoice | 120V · 80 |
| EQ-FN-MIX | Paint mixing and drying area equipment Finishing · Finish supply | 1 | $3,000 | $3,000 | TBD at invoice | 120V · 200 |
| EQ-FN-EXT | Exterior siding / stucco tool package Finishing · Construction supply | 1 | $4,000 | $4,000 | TBD at invoice | 120V · 150 |
| EQ-CT-MIX | Towable mixer (backup / remote) Concrete (field) · U.S. mixer dealer | 1 | $10,000 | $10,000 | TBD at invoice | engine · yard |
| EQ-CT-VIB | Concrete vibrators Concrete (field) · Wacker / similar | 4 | $800 | $3,200 | TBD at invoice | gas / electric · portable |
| EQ-CT-SCREED | Screeds (including entry laser) Concrete (field) · Somero-class used / conventional | 1 | $7,000 | $7,000 | TBD at invoice | engine · portable |
| EQ-CT-TROW | Power trowel Concrete (field) · Whiteman class | 1 | $3,000 | $3,000 | TBD at invoice | engine · portable |
| EQ-CT-WASH | Washout containment Concrete (field) · EHS supply | 1 | $2,000 | $2,000 | TBD at invoice | none · yard |
| EQ-CT-KIT | Slump / air / cylinder field kit Concrete (field) · Humboldt / Forney class | 1 | $3,300 | $3,300 | TBD at invoice | none · lab |
| EQ-CT-PUMP | Pump-access / hose / placement tools Concrete (field) · Concrete supply | 1 | $3,500 | $3,500 | TBD at invoice | none · portable |
| EQ-QC-COMP | Compression tester (small frame) or lab access + frame QC laboratory · Forney / Test Mark class | 1 | $10,000 | $10,000 | TBD at invoice | 230V · 120 |
| EQ-QC-BLOW | Blower-door kit QC laboratory · The Energy Conservatory / Retrotec | 1 | $5,000 | $5,000 | TBD at invoice | 120V · portable |
| EQ-QC-IR | Infrared camera QC laboratory · FLIR class | 1 | $3,000 | $3,000 | TBD at invoice | battery · portable |
| EQ-QC-EL | Electrical testers (lab set) QC laboratory · Fluke class | 1 | $3,500 | $3,500 | TBD at invoice | battery · lab |
| EQ-QC-PL | Plumbing pressure gauges / pumps QC laboratory · Test equipment | 1 | $2,000 | $2,000 | TBD at invoice | 120V · lab |
| EQ-QC-SURV | Laser levels + total station (shared field) QC laboratory · Leica / Topcon class | 1 | $7,000 | $7,000 | TBD at invoice | battery · portable |
| EQ-QC-DIM | Calipers / portable measurement QC laboratory · Mitutoyo class | 1 | $4,000 | $4,000 | TBD at invoice | battery · lab |
| EQ-QC-MOI | Moisture meters QC laboratory · Delmhorst / similar | 1 | $1,500 | $1,500 | TBD at invoice | battery · portable |
| EQ-QC-CAL | Calibration kit and torque tools QC laboratory · Calibration supply | 1 | $4,000 | $4,000 | TBD at invoice | none · lab |
| EQ-MN-WELD | Maintenance welder Maintenance · Miller class | 1 | $2,500 | $2,500 | TBD at invoice | 230V · shop |
| EQ-MN-DRILL | Drill press Maintenance · U.S. industrial | 1 | $1,500 | $1,500 | TBD at invoice | 120/230V · shop |
| EQ-MN-PRESS | Hydraulic press Maintenance · U.S. industrial | 1 | $3,000 | $3,000 | TBD at invoice | manual/hyd · shop |
| EQ-MN-MILL | Mill or combo machine (used) Maintenance · Used machine tool | 1 | $6,000 | $6,000 | TBD at invoice | 230V · shop |
| EQ-MN-WASH | Parts washer Maintenance · Safety-Kleen class | 1 | $1,500 | $1,500 | TBD at invoice | 120V · shop |
| EQ-MN-ALIGN | Alignment / lubrication tools Maintenance · Maint supply | 1 | $2,000 | $2,000 | TBD at invoice | none · shop |
| EQ-MN-SPARES | Spare motors, belts, sensors, PLC, valves, cylinders Maintenance · OEM + Grainger class | 1 | $8,500 | $8,500 | TBD at invoice | n/a · cage |
| EQ-AIR-MAIN | Rotary screw compressor Utilities (air) · Atlas Copco / Ingersoll / Quincy class | 1 | $13,000 | $13,000 | TBD at invoice | 460V 3Ø · utility |
| EQ-AIR-BAK | Backup compressor (used) Utilities (air) · Used industrial | 1 | $5,000 | $5,000 | TBD at invoice | 230/460V · utility |
| EQ-AIR-DRY | Dryer, receiver, filtration Utilities (air) · Same OEM | 1 | $8,000 | $8,000 | TBD at invoice | 230V · utility |
| EQ-AIR-PIPE | Distribution piping (equipment portion) Utilities (air) · AIRpipe / similar | 1 | $4,000 | $4,000 | TBD at invoice | n/a · plant |
| EQ-SF-GUARD | Machine guarding kits Safety · OSHA-compliant fabricators | 1 | $6,000 | $6,000 | TBD at invoice | n/a · machines |
| EQ-SF-LOTO | LOTO stations and locks Safety · Brady class | 1 | $2,000 | $2,000 | TBD at invoice | n/a · plant |
| EQ-SF-EYE | Eyewash stations Safety · Haws / similar | 1 | $2,500 | $2,500 | TBD at invoice | plumbed / portable · plant |
| EQ-SF-PPE | PPE stations (hearing, respirators, first aid) Safety · Safety supply | 1 | $2,500 | $2,500 | TBD at invoice | n/a · entries |
| EQ-SF-LIGHT | Light curtains (critical stations) Safety · Banner / similar | 1 | $3,000 | $3,000 | TBD at invoice | 24VDC · stations |
| EQ-AM-CARTS | Autonomous / guided carts (AMR class starter) Material movement · MiR / OTTO / similar class used or new | 2 | $35,000 | $70,000 | TBD at invoice | battery · aisles |
| EQ-AM-DOLLIES | Smart dollies / roller / pallet movement Material movement · In-house + industrial caster / conveyor | 1 | $25,000 | $25,000 | TBD at invoice | none/24V · cells |
| EQ-AM-TRACK | Location tracking (RFID / RTLS starter) Material movement · Zebra / Impinj class | 1 | $20,000 | $20,000 | TBD at invoice | PoE · plant |
| EQ-CV-STATIONS | Inspection cameras at critical stations Computer vision QC · Cognex / Keyence / similar class | 1 | $50,000 | $50,000 | TBD at invoice | 24VDC / PoE · stations |
| EQ-CV-SCAN | 3D / dimensional scan station Computer vision QC · Faro / similar class portable | 1 | $25,000 | $25,000 | TBD at invoice | 120V · QC |
| EQ-CV-DETECT | Defect-detection software + integration Computer vision QC · Vision OEM + integrator | 1 | $15,000 | $15,000 | TBD at invoice | n/a · n/a |
| EQ-KT-RACKS | Kitting racks / flow racks / supermarket Automated kitting · U.S. rack + in-house | 1 | $35,000 | $35,000 | TBD at invoice | n/a · warehouse |
| EQ-KT-PTL | Pick-to-light / barcode kitting Automated kitting · Lightning Pick / similar class | 1 | $20,000 | $20,000 | TBD at invoice | 24VDC · warehouse |
| EQ-KT-LABEL | Print / apply labeling for kits Automated kitting · Zebra class | 1 | $15,000 | $15,000 | TBD at invoice | 120V · warehouse |
| EQ-GD-ANDON | Station terminals / andon / scan-complete Guided stations · Industrial PC + scanners | 1 | $25,000 | $25,000 | TBD at invoice | 120V · stations |
| EQ-GD-WI | Digital work-instruction server Guided stations · MES module / VisualFactory class | 1 | $20,000 | $20,000 | TBD at invoice | n/a · n/a |
| EQ-ICF-CLAMP | Alignment / clamp assist Assisted ICF cell · In-house + pneumatic / servo kit | 1 | $40,000 | $40,000 | TBD at invoice | air / 480V · ICF |
| EQ-ICF-ADH | Adhesive dispense assist Assisted ICF cell · Graco / similar dispense | 1 | $25,000 | $25,000 | TBD at invoice | air / 120V · ICF |
| EQ-ICF-DIM | Dimensional fixtures / release assist Assisted ICF cell · In-house + sensors | 1 | $25,000 | $25,000 | TBD at invoice | 24VDC · ICF |
| EQ-ST-FEED | Measuring / feed assist Assisted steel / rebar · Cell integrator | 1 | $30,000 | $30,000 | TBD at invoice | 480V · rebar |
| EQ-ST-KITC | Kit conveyor / label Assisted steel / rebar · Conveyor + Zebra | 1 | $25,000 | $25,000 | TBD at invoice | 230V · rebar |
| EQ-ST-ASSIST | Tie / weld assist (not a full robot cell) Assisted steel / rebar · Positioner + tooling | 1 | $15,000 | $15,000 | TBD at invoice | 230V · steel |
| EQ-PDM-SENS | Vibration / temperature / current sensors Predictive maintenance · Fluke / Banner / similar class | 1 | $20,000 | $20,000 | TBD at invoice | 24VDC / battery · machines |
| EQ-PDM-GATE | Gateway / historian Predictive maintenance · Ignition / similar class | 1 | $15,000 | $15,000 | TBD at invoice | 120V · IT closet |
| EQ-CTL-PLC | PLC / safety PLC / HMI integration Controls / integration · Siemens / Allen-Bradley class | 1 | $20,000 | $20,000 | TBD at invoice | 24VDC · lab + floor |
| EQ-CTL-COMM | Commissioning / cell integration labor Controls / integration · Integrator (RFQ) | 1 | $15,000 | $15,000 | TBD at invoice | n/a · n/a |
| EQ-MH-FORK | Sit-down forklifts (used / late-model) Material handling · Toyota / Hyster dealer | 2 | $32,000 | $64,000 | TBD at invoice | LP or electric · aisles |
| EQ-MH-PAL | Electric pallet jacks Material handling · Crown / Toyota class | 3 | $3,500 | $10,500 | TBD at invoice | battery · floor |
| EQ-MH-GANTRY | Gantry crane (5-ton class) Material handling · Spanco / Gorbel class | 1 | $28,000 | $28,000 | TBD at invoice | 230/460V · assembly |
| EQ-MH-JIB | Jib cranes Material handling · Gorbel class | 2 | $6,500 | $13,000 | TBD at invoice | none/electric · cells |
| EQ-MH-VAC | Vacuum / panel lifters Material handling · Anver / similar | 1 | $12,000 | $12,000 | TBD at invoice | air / electric · portable |
| EQ-MH-DOCK | Dock levelers Material handling · Rite-Hite class / used | 4 | $4,500 | $18,000 | TBD at invoice | hyd · docks |
| EQ-MH-RACK | Cantilever, pallet, steel, lumber racks Material handling · U.S. rack | 1 | $4,500 | $4,500 | TBD at invoice | n/a · warehouse |
| EQ-FL-T1 | Class 8 tractor (used) Transport · U.S. used truck dealer | 1 | $48,000 | $48,000 | TBD at invoice | diesel · yard |
| EQ-FL-FB | Flatbed trailers Transport · U.S. trailer (Fontaine / similar used) | 2 | $18,000 | $36,000 | TBD at invoice | n/a · yard |
| EQ-FL-SEC | Load securement, GPS, ELD, DOT kit Transport · DOT / Qualcomm class | 1 | $7,000 | $7,000 | TBD at invoice | 12V · cabs |
| EQ-FL-RIG | Rigging, spreader, slings, shackles Site erection · Lift-All / similar | 1 | $9,000 | $9,000 | TBD at invoice | n/a · truck |
| EQ-IT-WS | Engineering workstations Digital factory · Dell / HP U.S. CAD class | 4 | $3,500 | $14,000 | TBD at invoice | 120V · office |
| EQ-IT-MON | Dual / ultrawide monitors Digital factory · Dell / LG | 1 | $4,000 | $4,000 | TBD at invoice | 120V · office |
| EQ-IT-LAP | Engineering / field laptops Digital factory · Dell / Lenovo | 4 | $1,500 | $6,000 | TBD at invoice | 120V · portable |
| EQ-IT-PLOT | Large-format plotter Digital factory · HP DesignJet class | 1 | $6,500 | $6,500 | TBD at invoice | 120V · print |
| EQ-IT-SCAN | Document scanner Digital factory · Fujitsu class | 1 | $1,500 | $1,500 | TBD at invoice | 120V · office |
| EQ-IT-3DP | 3D printer (fixture / prototype) Digital factory · U.S. desktop industrial | 1 | $2,400 | $2,400 | TBD at invoice | 120V · lab |
| EQ-IT-TAB | Shop-floor tablets Digital factory · iPad / Windows rugged-lite | 8 | $500 | $4,000 | TBD at invoice | Wi-Fi · stations |
| EQ-IT-RUG | Rugged field tablets Digital factory · Panasonic Toughbook class | 4 | $900 | $3,600 | TBD at invoice | battery · field |
| EQ-IT-BAR | Barcode printers and scanners Digital factory · Zebra class | 1 | $4,500 | $4,500 | TBD at invoice | 120V · plant |
| EQ-IT-NAS | NAS / server Digital factory · Synology / Dell | 1 | $5,000 | $5,000 | TBD at invoice | 120V + UPS · IT closet |
| EQ-IT-NET | Switches and Wi-Fi 6 APs Digital factory · Cisco / Ubiquiti class | 1 | $4,500 | $4,500 | TBD at invoice | PoE · plant |
| EQ-IT-FW | Firewall and UPS Digital factory · Fortinet / APC class | 1 | $3,500 | $3,500 | TBD at invoice | 120V · IT closet |
| EQ-IT-PLC | PLC / HMI engineering station (lab) Digital factory · Siemens / Rockwell class laptop + licenses | 1 | $14,000 | $14,000 | TBD at invoice | 120V · lab |
| EQ-SW-BIM | Revit / AutoCAD / Navisworks seats Software year-1 · Autodesk | 1 | $12,000 | $12,000 | License — not a serial | n/a · n/a |
| EQ-SW-STR | Structural analysis seat Software year-1 · RISA / Enercalc class | 1 | $4,000 | $4,000 | License — not a serial | n/a · n/a |
| EQ-SW-ERP | ERP / MES + machine connectivity Software year-1 · U.S. SMB manufacturing (JobBOSS / similar class) + OT integrator | 1 | $48,000 | $48,000 | License — not a serial | n/a · n/a |
| EQ-SW-SCHED | Production scheduler / factory dashboard Software year-1 · MES module + commercial AI APIs | 1 | $22,000 | $22,000 | License — not a serial | n/a · n/a |
| EQ-SW-TWIN | Digital twin / production data layer Software year-1 · OpenUSD + plant database | 1 | $18,000 | $18,000 | License — not a serial | n/a · n/a |
| EQ-SW-TRACE | House serial / digital birth certificate Software year-1 · QMS + MES genealogy | 1 | $12,000 | $12,000 | License — not a serial | n/a · n/a |
| EQ-SW-QMS | QMS / document control Software year-1 · Cloud QMS SMB | 1 | $4,000 | $4,000 | License — not a serial | n/a · n/a |
| EQ-SW-CRM | CRM Software year-1 · HubSpot / similar | 1 | $2,000 | $2,000 | License — not a serial | n/a · n/a |
| EQ-SW-WMS | Inventory / barcode software Software year-1 · ERP module or Fishbowl class | 1 | $2,500 | $2,500 | License — not a serial | n/a · n/a |
| EQ-SW-EST | Estimating / scheduling Software year-1 · MS Project / builder software | 1 | $2,000 | $2,000 | License — not a serial | n/a · n/a |
Phased — on purpose
| Item | When | Later estimate |
|---|---|---|
| EPS pre-expander, silos, steam boiler, shape molding, ICF mold family, CFS joist mill | RFQ / Phase 2 — not by raiding the $1,000,000 building | ICF cell ~$140–290k; CFS mill ~$190–340k; commercial form plant $1.2–2.5M |
| In-house concrete batch plant with silos and reclaim | Phase 2 | 350–600k |
| Fiber laser, tube laser, powder-coat line, robotic weld | Phase 2–3 | 400–900k |
| CNC stone / waterjet full countertop cell | Phase 2 | 150–300k |
| Second Class 8 tractor, step-deck, reach truck, mini-ex, skid, compactors, telehandler, pickup | When utilization pays (Year-1 rentals from WC) | 195k to buy |
| Owned mobile crane | When utilization pays | 180–350k used |
| Overhead bridge crane | Phase 2 building | 150–400k |
| Collaborative palletizer (UR10e / UR20 or FANUC CRX) — first robot that earns a cell | Phase 2 — after labor-hours data | 55–95k |
| Robotic MIG cell for apartment/hotel frames | Phase 2 (commercial only) | 140–320k |
| Full AGV fleet, robotic fastening, robotic paint, plant-wide vision | Phase II/III after measured bottlenecks — not this $550k envelope | the rest of the ~$3.6M vision |
| Hotel bathroom-pod line + IBC fire-tested assemblies | Phase 2–3 | 80k–250k tools + lab retainers |
| 80–120k SF commercial module plant (apartments / hotels) | Phase 3 | 8–18M |
| KUKA / similar automated modular-house factory | Not this company yet | 8–25M |
| Regional factories / hubs (SE, TX, MW, NE, Mountain West, West Coast) | Phase 3 | each a new file |
| Public streets, street lighting, and 12-acre campus infrastructure | Never inside $5M — extra acres are a separate development file | 1.5–4M+ of civil, before any building |
| Separate $1M STEM / AI center building | Later. Phase I is a 1,000–1,500 SF lab inside the hall | 1M+ |
| Year of $200k–$300k executive salaries before revenue | Never inside $350k payroll bucket | 1.2M+/yr |
| HUD-code manufactured-housing plant and IPIA/DAPIA path | Only if deliberately chosen later | separate certification |
| Second production line (20 homes/month) | After this line is proven | later 504/7(a) |
Caught and put in the budget
- Transportation tractor, trailers, securement, DOT, ELD, GPS, permits
- Pickup and telehandler rented from working capital; rigging owned; mini-ex, skid and compactors rented until utilization pays
- Contracted mobile crane budgeted in working capital — not pretended as owned
- Site development and stormwater — not just a pretty parking lot
- Fire sprinkler, generator/ATS, dust/weld exhaust, security
- QC lab, blower door, compression access, calibration
- First-article demonstration pad at the gate — the house is production COGS, not three walkthroughs stuffed into $100k
- Maintenance spares (motors, sensors, PLC, pneumatics)
- OSHA guarding, LOTO, eyewash, PPE, SDS — booked hardware; SHARP is later recognition, not a reason to cut this kit
- Digital thread: MES, BIM, scheduler, birth certificate, Autodesk seats at $12,000
- Day-1 automation cells that attack labor-hours — movement, vision QC, kitting, guided stations, ICF/steel assist, PdM, PLC
- 1,000–1,500 SF Intelligent Manufacturing Lab inside the hall — not a separate STEM building
- 50-state certification as an organization, not a machine
- Ameridura Homes marketing launch — site, brand, kits, CRM, first digital
- $400,000 cash reserve — cash is an automation system
- 10% cash equity stated as additional — ceiling not quietly raised
- Building $/SF honesty (used shell, not Class A new)
- Payroll honesty (elite core, not mature-company exec row)
Collateral summary — $3,448,500 listed
Lender haircut will be lower. Day-0 A/R and WIP are zero. Real estate register $1,700,000. Pledgeable equipment $1,573,500. The as-completed sheet and BPO are /collateral.
| Class | Description | Estimate | Lien |
|---|---|---|---|
| real-estate | 7-acre plant — Old Gentilly industrial corridor (NASA / Folgers street) The location pin is NASA Michoud Assembly Facility, 13800 Old Gentilly Road, New Orleans, LA 70129. The factory occupies 7 acres directly across that paved industrial street, on the same built-out strip as Folgers at 14601 and the Michoud Boulevard warehouses. The researched vacant tract across from 13800 is 55197 Old Gentilly Road (12.70 acres, MLS 2492745, $275,000 ask as of September 2026) — not owned. Adjacency is a manufacturing-location factor. It is not a NASA contract and it is not an appraisal. Purchase contract, survey, title, Phase I ESA, geotech, flood determination. Cost target, not a BPO. | $500,000 | First mortgage / 504 first + CDC second if stacked |
| real-estate | 40,000 SF factory — collateral once the structure is erected Building $1,000,000 + site $300,000. Used/relocated shell. This is not ‘nothing’ because it is not standing on application day. As-completed BPO / 504 appraisal is the opinion. Landlord waiver if leased instead of owned. | $1,200,000 | Same real-estate stack as land — as-completed mortgage |
| equipment | Phase I machines, handling, fleet, and IT hardware that can take a UCC or a title Software seats are excluded. Serials from vendor invoices. | $1,573,500 | UCC-1 blanket + specific filings on CNC / plasma / rebar / booth; titles on tractors, trailers, pickup, telehandler, mini-ex, skid |
| inventory | Initial raw materials and components (forms, rebar, steel, lumber, openings, MEP, finishes, appliances) Turns. Advance rate will be a fraction of cost. First-article materials included. | $175,000 | UCC inventory / proceeds |
| inventory | WIP and finished assemblies (once producing) Zero on Day 0. Becomes real after first houses enter the bay. Do not collateralize hoped-for WIP. | $0 | UCC inventory |
| other | Equipment deposits / progress payments Filled when quotes exist. Lender wants invoices, not a wish list. | $0 | Assignment of deposits where the vendor will sign |
| accounts | Accounts receivable (developer invoices) Zero until offtake ships. Not a Day-1 borrowing base. | $0 | UCC accounts / proceeds |
Real-estate register
| SKU | Description | Qty | Value | Serial / VIN | Lien |
|---|---|---|---|---|---|
| RE-LAND-7AC | 7-acre plant — Old Gentilly corridor Old Gentilly Road industrial corridor, New Orleans East. Across from NASA at 13800 Old Gentilly Road, New Orleans, LA 70129. Target listing 55197 Old Gentilly Road, New Orleans, LA 70129 (not owned). Same street as Folgers. Not an appraisal. | 1 | $500,000 | Legal description TBD — purchase contract / survey | First mortgage / 504 stack |
| RE-BLDG-001 | Used / relocated steel high-bay shell (~40,000 SF, 170' × 235') Used / relocated industrial — not Class A new. Collateral once erected. | 1 | $520,000 | As-built / contractor pay app TBD | Mortgage / 504 — as-completed plant |
| RE-BLDG-002 | Reinforced industrial slab (crane / fixture loads) Used / relocated industrial — not Class A new. Collateral once erected. | 1 | $205,000 | As-built / contractor pay app TBD | Mortgage / 504 — as-completed plant |
| RE-BLDG-003 | Overhead doors and four truck docks Used / relocated industrial — not Class A new. Collateral once erected. | 1 | $68,000 | As-built / contractor pay app TBD | Mortgage / 504 — as-completed plant |
| RE-BLDG-004 | Offices, lockers, break room, first aid, training Used / relocated industrial — not Class A new. Collateral once erected. | 1 | $45,000 | As-built / contractor pay app TBD | Mortgage / 504 — as-completed plant |
| RE-BLDG-005 | Electrical service, panels, LED, generator / ATS, utility drops Used / relocated industrial — not Class A new. Collateral once erected. | 1 | $85,000 | As-built / contractor pay app TBD | Mortgage / 504 — as-completed plant |
| RE-BLDG-006 | Fire alarm and sprinkler Used / relocated industrial — not Class A new. Collateral once erected. | 1 | $45,000 | As-built / contractor pay app TBD | Mortgage / 504 — as-completed plant |
| RE-BLDG-007 | HVAC for occupied areas + plant ventilation share Used / relocated industrial — not Class A new. Collateral once erected. | 1 | $20,000 | As-built / contractor pay app TBD | Mortgage / 504 — as-completed plant |
| RE-BLDG-008 | Security cameras and access control Used / relocated industrial — not Class A new. Collateral once erected. | 1 | $12,000 | As-built / contractor pay app TBD | Mortgage / 504 — as-completed plant |
| RE-SITE-001 | Pad / yard clearing and rough grade (not 7-acre mass fill) Site work on the NASA / Folgers industrial street | 1 | $40,000 | Civil as-builts TBD | Mortgage / 504 — as-completed plant |
| RE-SITE-002 | Drainage and stormwater for the yard Site work on the NASA / Folgers industrial street | 1 | $32,000 | Civil as-builts TBD | Mortgage / 504 — as-completed plant |
| RE-SITE-003 | Heavy truck drives and aggregate yards Site work on the NASA / Folgers industrial street | 1 | $48,000 | Civil as-builts TBD | Mortgage / 504 — as-completed plant |
| RE-SITE-004 | Short utility taps (water, sewer/septic, electric, gas) — not a long main Site work on the NASA / Folgers industrial street | 1 | $45,000 | Civil as-builts TBD | Mortgage / 504 — as-completed plant |
| RE-SITE-005 | Fencing, gates, exterior lighting Site work on the NASA / Folgers industrial street | 1 | $18,000 | Civil as-builts TBD | Mortgage / 504 — as-completed plant |
| RE-SITE-006 | Minimal employee parking Site work on the NASA / Folgers industrial street | 1 | $5,000 | Civil as-builts TBD | Mortgage / 504 — as-completed plant |
| RE-SITE-007 | Signage Site work on the NASA / Folgers industrial street | 1 | $2,000 | Civil as-builts TBD | Mortgage / 504 — as-completed plant |
| RE-SITE-008 | Trailer and finished-product gravel staging Site work on the NASA / Folgers industrial street | 1 | $10,000 | Civil as-builts TBD | Mortgage / 504 — as-completed plant |
Equipment / vehicle register
| SKU | Description | Qty | Value | Serial / VIN | Lien |
|---|---|---|---|---|---|
| EQ-ICF-CNC | CNC foam / hot-wire cutter U.S. foam CNC (Hotwire / similar) or equivalent — quote TBD | 1 | $38,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ICF-HW | Secondary hot-wire station Domestic foam-cut supplier — quote TBD | 1 | $6,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ICF-TABLES | ICF assembly tables U.S. fab / in-house steel — quote TBD | 4 | $10,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ICF-JIGS | Wall jigs and alignment fixtures In-house + local fab — quote TBD | 1 | $20,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ICF-FIXTURES | Corner / T / end / buck / lintel fixtures In-house + local fab — quote TBD | 1 | $7,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ICF-LABEL | ICF labeling / barcode station Zebra / Honeywell class — quote TBD | 1 | $3,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-RB-CNC | CNC rebar bender U.S./NA dealer (KRB, Schnell, or used domestic) — quote TBD | 1 | $58,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-RB-CUT | Rebar cutter U.S. construction-equip dealer — quote TBD | 1 | $14,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-RB-STIR | Stirrup bender NA dealer — quote TBD | 1 | $12,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-RB-STR | Straightener / decoiler (right-sized / used) Used industrial — quote TBD | 1 | $8,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-RB-JIG | Cage / wall / opening / beam jigs In-house fab — quote TBD | 1 | $8,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-RB-TIE | Automatic rebar tying tools MAX / similar — quote TBD | 2 | $4,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-RB-TAG | Rebar tagging / mill-cert station Label + rack — quote TBD | 1 | $1,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ST-PLASMA | CNC plasma table (4×8 class) U.S. (Hypertherm table class / used) — quote TBD | 1 | $38,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ST-IRON | Ironworker Scotchman / similar U.S. — quote TBD | 1 | $12,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ST-SHEAR | Hydraulic shear (small) Used industrial — quote TBD | 1 | $8,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ST-BRAKE | Press brake (40–60T used) Used U.S. dealer — quote TBD | 1 | $12,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ST-BAND | Band saw U.S. industrial — quote TBD | 1 | $5,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ST-COLD | Cold saw U.S. industrial — quote TBD | 1 | $3,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ST-DRILL | Drill press + magnetic drills Milwaukee / similar — quote TBD | 1 | $3,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ST-MIG | MIG welders Miller / Lincoln U.S. — quote TBD | 4 | $10,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ST-TIG | TIG welder Miller / Lincoln U.S. — quote TBD | 1 | $2,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ST-TABLES | Welding tables, fixtures, curtains U.S. weld-table — quote TBD | 1 | $6,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ST-FUME | Welding fume extraction (cell) Lincoln / Donaldson class — quote TBD | 1 | $8,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-FR-PANEL | CNC panel saw U.S. wood CNC / used panel saw — quote TBD | 1 | $18,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-FR-BEAM | Beam saw Construction saw dealer — quote TBD | 1 | $7,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-FR-SAWS | Table / miter / chop saw package SawStop + DeWalt class — quote TBD | 1 | $6,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-FR-ROUTER | CNC router (shared with cabinets) U.S. CNC (ShopSabre / similar class) — quote TBD | 1 | $18,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-FR-TABLES | Floor and roof assembly / framing tables In-house + truss-table analog — quote TBD | 1 | $22,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-FR-AIR | Pneumatic nailers / screw systems Paslode / Milwaukee class — quote TBD | 1 | $6,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-FR-ADH | Adhesive and membrane stations Construction supply — quote TBD | 1 | $4,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-FR-LIFT | Floor / roof lifting fixtures In-house + rigging shop — quote TBD | 1 | $15,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-EL-CUT | Automatic wire cutter / stripper Komax class / Schleuniger used — quote TBD | 1 | $8,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-EL-CRIMP | Crimp / terminal / wire-label kit Panduit / Brady class — quote TBD | 1 | $4,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-EL-BOARD | Harness boards and electrical benches In-house — quote TBD | 1 | $5,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-EL-COND | Conduit bender + cutter Greenlee class — quote TBD | 1 | $3,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-EL-TEST | Electrical test kit (megger, GFCI, continuity) Fluke class — quote TBD | 1 | $4,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-EL-PANEL | Panelboard assembly station In-house + Square D / Eaton components — quote TBD | 1 | $5,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-PL-PEX | PEX cutter / expander / crimp kit Uponor / Milwaukee class — quote TBD | 1 | $3,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-PL-MAN | Plumbing manifold / module fixtures In-house — quote TBD | 1 | $5,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-PL-TEST | Plumbing pressure / leak test station Test-pump dealers — quote TBD | 1 | $3,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-HV-PLASMA | Small duct plasma cutter U.S. HVAC plasma (used/new) — quote TBD | 1 | $12,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-HV-PITT | Pittsburgh lock + brake Lockformer class / used — quote TBD | 1 | $10,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-HV-SEAM | Seamer / insulation / seal station HVAC supply — quote TBD | 1 | $4,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CB-SAW | Cabinet panel saw Used SCM / Altendorf class — quote TBD | 1 | $10,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CB-EDGE | Edgebander Used Holz-Her / SCM class — quote TBD | 1 | $12,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CB-BORE | Hinge boring / drilling Blum / Maggi class — quote TBD | 1 | $6,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CB-ASM | Cabinet assembly tables and clamps In-house — quote TBD | 1 | $5,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CB-HW | Hardware insertion station Cabinet supply — quote TBD | 1 | $2,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CB-TOP | Countertop cutting (bridge saw used) Used stone saw — not waterjet — quote TBD | 1 | $4,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CB-BATH | Shower / waterproofing station Schluter / similar system tools — quote TBD | 1 | $3,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-WD-TABLE | Glazing / window assembly tables In-house — quote TBD | 1 | $4,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-WD-LIFT | Glass suction lifters Wood’s / similar — quote TBD | 1 | $3,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-WD-SEAL | Sealant dispensing U.S. dispensing — quote TBD | 1 | $3,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-WD-DOOR | Door fixtures and hardware station In-house + hardware — quote TBD | 1 | $5,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-FN-BOOTH | Paint spray booth U.S. booth (Garmat class / used) — quote TBD | 1 | $16,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-FN-SPRAY | Airless / HVLP sprayers Graco class — quote TBD | 1 | $5,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-FN-DW | Drywall cutting, lifts, taping tools Construction supply — quote TBD | 1 | $6,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-FN-FL | Flooring / tile saws MK / similar — quote TBD | 1 | $4,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-FN-MIX | Paint mixing and drying area equipment Finish supply — quote TBD | 1 | $3,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-FN-EXT | Exterior siding / stucco tool package Construction supply — quote TBD | 1 | $4,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CT-MIX | Towable mixer (backup / remote) U.S. mixer dealer — quote TBD | 1 | $10,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CT-VIB | Concrete vibrators Wacker / similar — quote TBD | 4 | $3,200 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CT-SCREED | Screeds (including entry laser) Somero-class used / conventional — quote TBD | 1 | $7,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CT-TROW | Power trowel Whiteman class — quote TBD | 1 | $3,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CT-WASH | Washout containment EHS supply — quote TBD | 1 | $2,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CT-KIT | Slump / air / cylinder field kit Humboldt / Forney class — quote TBD | 1 | $3,300 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CT-PUMP | Pump-access / hose / placement tools Concrete supply — quote TBD | 1 | $3,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-QC-COMP | Compression tester (small frame) or lab access + frame Forney / Test Mark class — quote TBD | 1 | $10,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-QC-BLOW | Blower-door kit The Energy Conservatory / Retrotec — quote TBD | 1 | $5,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-QC-IR | Infrared camera FLIR class — quote TBD | 1 | $3,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-QC-EL | Electrical testers (lab set) Fluke class — quote TBD | 1 | $3,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-QC-PL | Plumbing pressure gauges / pumps Test equipment — quote TBD | 1 | $2,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-QC-SURV | Laser levels + total station (shared field) Leica / Topcon class — quote TBD | 1 | $7,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-QC-DIM | Calipers / portable measurement Mitutoyo class — quote TBD | 1 | $4,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-QC-MOI | Moisture meters Delmhorst / similar — quote TBD | 1 | $1,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-QC-CAL | Calibration kit and torque tools Calibration supply — quote TBD | 1 | $4,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-MN-WELD | Maintenance welder Miller class — quote TBD | 1 | $2,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-MN-DRILL | Drill press U.S. industrial — quote TBD | 1 | $1,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-MN-PRESS | Hydraulic press U.S. industrial — quote TBD | 1 | $3,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-MN-MILL | Mill or combo machine (used) Used machine tool — quote TBD | 1 | $6,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-MN-WASH | Parts washer Safety-Kleen class — quote TBD | 1 | $1,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-MN-ALIGN | Alignment / lubrication tools Maint supply — quote TBD | 1 | $2,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-MN-SPARES | Spare motors, belts, sensors, PLC, valves, cylinders OEM + Grainger class — quote TBD | 1 | $8,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-AIR-MAIN | Rotary screw compressor Atlas Copco / Ingersoll / Quincy class — quote TBD | 1 | $13,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-AIR-BAK | Backup compressor (used) Used industrial — quote TBD | 1 | $5,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-AIR-DRY | Dryer, receiver, filtration Same OEM — quote TBD | 1 | $8,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-AIR-PIPE | Distribution piping (equipment portion) AIRpipe / similar — quote TBD | 1 | $4,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | Mortgage + UCC — counsel calls fixture vs equipment |
| EQ-SF-GUARD | Machine guarding kits OSHA-compliant fabricators — quote TBD | 1 | $6,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-SF-LOTO | LOTO stations and locks Brady class — quote TBD | 1 | $2,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-SF-EYE | Eyewash stations Haws / similar — quote TBD | 1 | $2,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-SF-PPE | PPE stations (hearing, respirators, first aid) Safety supply — quote TBD | 1 | $2,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-SF-LIGHT | Light curtains (critical stations) Banner / similar — quote TBD | 1 | $3,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-AM-CARTS | Autonomous / guided carts (AMR class starter) MiR / OTTO / similar class used or new — quote TBD | 2 | $70,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-AM-DOLLIES | Smart dollies / roller / pallet movement In-house + industrial caster / conveyor — quote TBD | 1 | $25,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-AM-TRACK | Location tracking (RFID / RTLS starter) Zebra / Impinj class — quote TBD | 1 | $20,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CV-STATIONS | Inspection cameras at critical stations Cognex / Keyence / similar class — quote TBD | 1 | $50,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CV-SCAN | 3D / dimensional scan station Faro / similar class portable — quote TBD | 1 | $25,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CV-DETECT | Defect-detection software + integration Vision OEM + integrator — quote TBD | 1 | $15,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-KT-RACKS | Kitting racks / flow racks / supermarket U.S. rack + in-house — quote TBD | 1 | $35,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-KT-PTL | Pick-to-light / barcode kitting Lightning Pick / similar class — quote TBD | 1 | $20,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-KT-LABEL | Print / apply labeling for kits Zebra class — quote TBD | 1 | $15,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-GD-ANDON | Station terminals / andon / scan-complete Industrial PC + scanners — quote TBD | 1 | $25,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-GD-WI | Digital work-instruction server MES module / VisualFactory class — quote TBD | 1 | $20,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ICF-CLAMP | Alignment / clamp assist In-house + pneumatic / servo kit — quote TBD | 1 | $40,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ICF-ADH | Adhesive dispense assist Graco / similar dispense — quote TBD | 1 | $25,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ICF-DIM | Dimensional fixtures / release assist In-house + sensors — quote TBD | 1 | $25,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ST-FEED | Measuring / feed assist Cell integrator — quote TBD | 1 | $30,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ST-KITC | Kit conveyor / label Conveyor + Zebra — quote TBD | 1 | $25,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-ST-ASSIST | Tie / weld assist (not a full robot cell) Positioner + tooling — quote TBD | 1 | $15,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-PDM-SENS | Vibration / temperature / current sensors Fluke / Banner / similar class — quote TBD | 1 | $20,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-PDM-GATE | Gateway / historian Ignition / similar class — quote TBD | 1 | $15,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CTL-PLC | PLC / safety PLC / HMI integration Siemens / Allen-Bradley class — quote TBD | 1 | $20,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-CTL-COMM | Commissioning / cell integration labor Integrator (RFQ) — quote TBD | 1 | $15,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-MH-FORK | Sit-down forklifts (used / late-model) Toyota / Hyster dealer — quote TBD | 2 | $64,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-MH-PAL | Electric pallet jacks Crown / Toyota class — quote TBD | 3 | $10,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-MH-GANTRY | Gantry crane (5-ton class) Spanco / Gorbel class — quote TBD | 1 | $28,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | Mortgage + UCC — counsel calls fixture vs equipment |
| EQ-MH-JIB | Jib cranes Gorbel class — quote TBD | 2 | $13,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | Mortgage + UCC — counsel calls fixture vs equipment |
| EQ-MH-VAC | Vacuum / panel lifters Anver / similar — quote TBD | 1 | $12,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-MH-DOCK | Dock levelers Rite-Hite class / used — quote TBD | 4 | $18,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | Mortgage + UCC — counsel calls fixture vs equipment |
| EQ-MH-RACK | Cantilever, pallet, steel, lumber racks U.S. rack — quote TBD | 1 | $4,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-FL-T1 | Class 8 tractor (used) U.S. used truck dealer — quote TBD | 1 | $48,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | Title / lender as lienholder when purchased |
| EQ-FL-FB | Flatbed trailers U.S. trailer (Fontaine / similar used) — quote TBD | 2 | $36,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | Title / lender as lienholder when purchased |
| EQ-FL-SEC | Load securement, GPS, ELD, DOT kit DOT / Qualcomm class — quote TBD | 1 | $7,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-FL-RIG | Rigging, spreader, slings, shackles Lift-All / similar — quote TBD | 1 | $9,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-IT-WS | Engineering workstations Dell / HP U.S. CAD class — quote TBD | 4 | $14,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-IT-MON | Dual / ultrawide monitors Dell / LG — quote TBD | 1 | $4,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-IT-LAP | Engineering / field laptops Dell / Lenovo — quote TBD | 4 | $6,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-IT-PLOT | Large-format plotter HP DesignJet class — quote TBD | 1 | $6,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-IT-SCAN | Document scanner Fujitsu class — quote TBD | 1 | $1,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-IT-3DP | 3D printer (fixture / prototype) U.S. desktop industrial — quote TBD | 1 | $2,400 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-IT-TAB | Shop-floor tablets iPad / Windows rugged-lite — quote TBD | 8 | $4,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-IT-RUG | Rugged field tablets Panasonic Toughbook class — quote TBD | 4 | $3,600 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-IT-BAR | Barcode printers and scanners Zebra class — quote TBD | 1 | $4,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-IT-NAS | NAS / server Synology / Dell — quote TBD | 1 | $5,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-IT-NET | Switches and Wi-Fi 6 APs Cisco / Ubiquiti class — quote TBD | 1 | $4,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-IT-FW | Firewall and UPS Fortinet / APC class — quote TBD | 1 | $3,500 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-IT-PLC | PLC / HMI engineering station (lab) Siemens / Rockwell class laptop + licenses — quote TBD | 1 | $14,000 | TBD — issued on the vendor invoice / nameplate at commissioning. Not invented in this file. | UCC-1 specific + blanket |
| EQ-SW-BIM | Revit / AutoCAD / Navisworks seats Autodesk — quote TBD | 1 | $12,000 | N/A — license, not collateral-quality | Do not count. Blanket UCC may attach; recovery is near zero. |
| EQ-SW-STR | Structural analysis seat RISA / Enercalc class — quote TBD | 1 | $4,000 | N/A — license, not collateral-quality | Do not count. Blanket UCC may attach; recovery is near zero. |
| EQ-SW-ERP | ERP / MES + machine connectivity U.S. SMB manufacturing (JobBOSS / similar class) + OT integrator — quote TBD | 1 | $48,000 | N/A — license, not collateral-quality | Do not count. Blanket UCC may attach; recovery is near zero. |
| EQ-SW-SCHED | Production scheduler / factory dashboard MES module + commercial AI APIs — quote TBD | 1 | $22,000 | N/A — license, not collateral-quality | Do not count. Blanket UCC may attach; recovery is near zero. |
| EQ-SW-TWIN | Digital twin / production data layer OpenUSD + plant database — quote TBD | 1 | $18,000 | N/A — license, not collateral-quality | Do not count. Blanket UCC may attach; recovery is near zero. |
| EQ-SW-TRACE | House serial / digital birth certificate QMS + MES genealogy — quote TBD | 1 | $12,000 | N/A — license, not collateral-quality | Do not count. Blanket UCC may attach; recovery is near zero. |
| EQ-SW-QMS | QMS / document control Cloud QMS SMB — quote TBD | 1 | $4,000 | N/A — license, not collateral-quality | Do not count. Blanket UCC may attach; recovery is near zero. |
| EQ-SW-CRM | CRM HubSpot / similar — quote TBD | 1 | $2,000 | N/A — license, not collateral-quality | Do not count. Blanket UCC may attach; recovery is near zero. |
| EQ-SW-WMS | Inventory / barcode software ERP module or Fishbowl class — quote TBD | 1 | $2,500 | N/A — license, not collateral-quality | Do not count. Blanket UCC may attach; recovery is near zero. |
| EQ-SW-EST | Estimating / scheduling MS Project / builder software — quote TBD | 1 | $2,000 | N/A — license, not collateral-quality | Do not count. Blanket UCC may attach; recovery is near zero. |
Future collateral — identified, not pledged
Phase II planning midpoint $5,936,000. Phase III (second plant / KUKA class) $30,465,000. Combined identified $36,401,000. No UCC until the invoice exists. Full named stack is on /in-house.
| SKU | Asset | Phase | Planning value | Lien when purchased |
|---|---|---|---|---|
| EQ-FUT-R-COBOT-PALLET | Collaborative palletizing cell Universal Robots UR10e / UR20 or FANUC CRX with PalletPRO; Robotiq grippers | 2 | $75,000 | UCC-1 when purchased |
| EQ-FUT-R-COBOT-TEND | Machine-tending cobot UR10e or FANUC CRX-10iA/L | 2 | $67,500 | UCC-1 when purchased |
| EQ-FUT-EPS-PRE | Batch or continuous pre-expander + aging silos + convey Modix USA / Dongshan / Epsole class | 2 | $300,000 | UCC-1 when purchased |
| EQ-FUT-EPS-PRESS | Shape-moulding press (SPZ-140TE class, ~1,200×1,400 mm, ~8.5 t) Ebid Toys SPZ-140TE class / Modix USA / Dongshan. Prefer U.S. support for SBA collateral. | 2 | $200,000 | UCC-1 when purchased |
| EQ-FUT-EPS-MOULDS | Straight, corner, T, lintel, buck, half-height moulds Same press OEM + independent mould shop | 2 | $450,000 | UCC-1 when purchased |
| EQ-FUT-EPS-STEAM | 1–4 t/h boiler, accumulator, vacuum, cooling tower, compressor Cleaver-Brooks / Miura class boiler (U.S.) + EPS-line auxiliaries | 2 | $465,000 | Fixture vs UCC — counsel at purchase |
| EQ-FUT-EPS-RECYCLE | EPS crusher / densifier / reclaim INTCO / GreenMax class or EPS-line OEM | 2 | $80,000 | UCC-1 when purchased |
| EQ-FUT-EPS-BUILDING | Dedicated EPS / ICF manufacturing bay (Zone J on the 7-acre plant parcel) Metal building — separate from the 40,000-SF house line (fire, steam, pentane) | 2 | $800,000 | Later 504 / mortgage |
| EQ-FUT-CT-BATCH | Ready-mix batch plant, silos, reclaim Vince Hagan / Erie Strayer / CTB class (used U.S. plants exist) | 2 | $475,000 | Fixture vs UCC — counsel at purchase |
| EQ-FUT-RB-AUTO-LINE | Rebar machining center Schnell / KRB / MEP / WEIBUILD class | 2 | $950,000 | UCC-1 when purchased |
| EQ-FUT-ST-FIBER | Fiber laser + shuttle table Mazak / TRUMPF / Cincinnati / used U.S. 4–6 kW | 2 | $400,000 | UCC-1 when purchased |
| EQ-FUT-ST-WELD-CELL | Robotic MIG cell + positioner Lincoln / Miller + FANUC Arc Mate or ABB IRB; or KUKA | 2 | $230,000 | UCC-1 when purchased |
| EQ-FUT-ST-POWDER | Powder booth + oven, or robotic coat later Gema / Nordson class | 2 | $150,000 | UCC-1 when purchased |
| EQ-FUT-MH-BRIDGE | Overhead bridge crane Konecranes / Street / Spanco class | 2 | $275,000 | Fixture vs UCC — counsel at purchase |
| EQ-FUT-MH-AMR | AMR / AGV fleet (2–6 units) MiR / OTTO Motors / Fetch | 3 | $260,000 | UCC-1 when purchased |
| EQ-FUT-FN-PAINT-BOT | Paint robot in the existing booth ABB IRB 5500 / FANUC Paint or a used integrator cell | 3 | $155,000 | UCC-1 when purchased |
| EQ-FUT-QC-SCAN | Laser tracker / 3D scanner cell FARO / Leica AT960 / Creaform | 2 | $92,500 | UCC-1 when purchased |
| EQ-FUT-CB-NESTING | Nesting CNC router + software SCM / Biesse / Homag class | 2 | $130,000 | UCC-1 when purchased |
| EQ-FUT-CB-WATERJET | CNC stone / waterjet Park Industries / Breton class | 2 | $225,000 | UCC-1 when purchased |
| EQ-FUT-HT-POD | Pod assembly line: waterproofing, fixtures, test, crate In-house fixtures + Schluter / Kerdi systems; not a branded robot line | 2 | $150,000 | UCC-1 when purchased |
| EQ-FUT-HT-STACK | Longer framing tables, stacking jigs, fire-board station In-house + Randek / Weinmann class panel line if wood; ICF remains our wall | 3 | $550,000 | UCC-1 when purchased |
| EQ-FUT-HT-SPRINKLER | Victaulic grooving + cut shop Victaulic / Ridgid / Wheeler-Rex | 2 | $26,000 | UCC-1 when purchased |
| EQ-FUT-MEP-AUTO | Industrial wire machine + PEX manifold CNC Komax / Schleuniger + Uponor industrial | 2 | $77,500 | UCC-1 when purchased |
| EQ-FUT-WD-DEPTH | Window/door assembly depth: tables, hardware, seal, test In-house + bought IGUs (Cardinal / similar). Never melt glass. | 2 | $52,500 | UCC-1 when purchased |
| EQ-FUT-HT-PLANT | 80,000–120,000 SF commercial module plant New or reused industrial — not the 40,000-SF house building stretched | 3 | $13,000,000 | Later 504 / mortgage |
| EQ-FUT-KUKA-LINE | KUKA / similar automated modular-house system KUKA automated modular house building | 3 | $16,500,000 | UCC-1 when purchased |
| EQ-FUT-FL-CRANE | All-terrain crane (owned when utilization pays) Grove / Liebherr / Tadano used | 2 | $265,000 | Title when purchased |
Lien package
- Unlimited personal guaranty — Philbert Andre Honore (20%+ owner)
- Blanket UCC-1 on the borrower (once formed): equipment, inventory, accounts, general intangibles
- Specific equipment list with serial numbers from invoices — the pledgeable register, not the software seats
- Vehicle titles with lender as lienholder (tractors, trailers, pickup, titled site equipment)
- First mortgage on land as-is; as-completed mortgage on the 40,000-SF plant and site once erected — 504 first / CDC second if stacked
- Assignment of leases and a landlord waiver if the plant is leased instead of purchased
- Assignment of key contracts (offtake, Manufacturing Leadership Agreement) if the lender requires
- Insurance: lender loss-payee on property, inland marine on equipment in transit, additional insured on GL, workers’ comp, auto, umbrella
- Life insurance on the principal as required by the lender
- Deposit account control if the lender requires (operating account of the manufacturer, not Paparazzi Marketing)
Not collateral
- Paparazzi Marketing Group LLC operating assets — affiliate, not this borrower, unless a separate pledge is negotiated and disclosed
- Ooh La La Boutique inventory
- The sister’s PhD, Terry’s résumé, or the board — those are credit factors, not collateral
- Software licenses, Autodesk seats, ERP subscriptions
- A contracted mobile crane the company does not own
- An EPS plant that is Phase 2 and not purchased
- Phase II/III in-house stack (foam press, batch plant, hotel line, KUKA factory) until invoiced
- Engineering, certification, payroll, and working-capital cash — spent, not lienable
- A NASA or Folgers relationship that has not been contracted — location is real; offtake is not
- Hoped-for 50-state approvals
- Paparazzi marketing receivables as if they were factory A/R
Never-blind checklist
- Every titled vehicle: VIN, title status, existing liens, insurance
- Every CNC / plasma / rebar / booth: make, model, serial, location, invoice
- Real estate: legal description, exceptions, environmental, flood zone, survey — Old Gentilly parcel, not a St. Tammany placeholder
- As-completed BPO / 504 appraisal that states NASA Michoud and Folgers as industrial neighbors
- Inventory: location, cost, slow-moving, consignment (none intended)
- Intercompany: no silent pledge of Paparazzi assets without affiliation disclosure
- Landlord waiver before any leasehold improvements are funded
- Replacement cost vs orderly liquidation — the lender will haircut this schedule